Full Concrete Slab
For Multi-Section Homes
Foundation
Specifications

Slide Show featuring our Foundation Construction Process:
Specifications
Formed to be Poured
Pouring Concrete
Completed Slab

Top View
 |
Concrete to be Portland
(C150) ASIP. C150. 3000 psi (@28 days.) |
 |
Water/Concrete ratio 0.60 moisture to be
maintained in concrete during the curing period. Longer periods of moist
curing required at lower temperatures. FM ratio 2.5 to 3.0. |
 |
Calcium choloride use in cold weather
concreting shall be limited to less than 2% by weight. |
 |
GENERAL SITE
PREPARATION: (Not Inclusive): Site to be dry (not frozen), protected from
rainfall and surface drainage. Loose granular or weak soil (i.e. topsoil)
to be removed. Pad site to be excavated level in all directions and
compacted. Subsurface drain for ground water protection of pad areas may
be required, subject to site conditions and the existence of groundwater
(table). |